Last week’s closures for Manchester’s Highway 13 Street Improvement Project will continue into this week.

The City says there was good progress on the water main getting installed at the main four corners of Main and Franklin and along West Main Street.

Today, crews will be working on the sidewalks at the intersection of Main and Franklin. They’ll also be doing the water service line crossing West Main at the alley on the west side of Advanced Eyecare Associates. They’ll also be removing the sidewalk on the south side of West Main from the bridge to Legion. And they’ll do some shoulder grading on West Main from 9th to 13th.

Tomorrow, they expect to work on the asphalt at Main and Franklin and north on Franklin to the south side of Fayette. They’ll also be replacing the sidewalk on the south side of West Main from the bridge to Legion tomorrow.